Reasons for Delay

...

General reasons 

Campus

...

hiring 

Massive effort by the Development team and QA team went into campus hiring. In taking multiple online interviews, campus visits etc. Campus hiring got closed recently.

New development team

New Joinees of last year joined our Dev and QA team around July, team herachiry got changed.  Senior folks became Team Leads, whose main responsibilities became planning and mentoring. While all development and QA tasks got assigned to our new Ninjas. Current sprint is their first ever sprint.

This caused 4 inevitable effects as

...

Poor timeline estimation as new developers take more time learning the code base

...

More back and forth in Dev review (Strict-er code review in initial days). 

...

More time in QA, as more small small issues. And New QAs doing themselves. 

...

.

...

Specific feature related reasons

Multiple

...

units of

...

measure (UOM) and Handling

...

Eaches and Packs

...

Unexpected edge cases in Bulk Break Part

Bulk break functionalities were not planned in depth when we communicated the timelines. Edge cases were not thrashed out for some scenarios like expiry etc. When we did that part of planning we realized that effort is a lot more than previously considered.When we started the development, we realised there are more edge cases in bulk break than what we anticipated

Major QA effort 

UOM feature has major changes in Inventory reservation workflow, we are adding new buckets and doing soft allocation to support bulk break.

...

We are moving towards full QA automation. One part of the QA team will only write new Automation test cases for new features and functionalities, the other part will just run the pre-defined scenarios for new features.

Updated Timelines

...

Epic or Features

...

Tentative Release dates

...

POS Integration support

...

30/Sep/22

...

Increase limits of "Print Bulk Items via CSV"

...

07/Oct/22

...

B2B picklist release search filters and Pick Order group

...

14/Oct/22

...

Order Accept / Reject Flow

...

21/Oct/22

...

Cluster picking | Pre pack staging and Pack box consolidation

...

04/Nov/22

...

Order Hopping and Store Schedule Support

...

11/Nov/22

...

Allow processing Returns of other warehouses

...

23/Nov/22

...